DETAILS OF STATE PLAN SCHEMES INDICATING SPILLOVER TO FINANCIAL YEAR  2009-10
NORTH DISTRICT ( MANGAN SUB-DIVISION & SUB- DIVISION- IV)
 MAJOR HEAD :- EXPANSION  (Rupees in lakh)
Sl. No NAME OF WORK Name of Contractor Date of Commencement Due date of Completion Year of Sanction Sanctioned Cost Expenditure Spillover to 2009-10 Physical Progress Remarks
Upto         2007-08 During 2008-09 Total  
1 2 3 4 5 6 7 8 9 10 11 12 13
                         
b. SUB-DIVISION :-  No. IV                      
1 Premix Carpetting on Penlong Tintek Road km 12th to 20th Suresh Mundra 28.11.02 31.5.06 2000 158.79 99.64 0.00 99.64 59.15 66%  
2 Upgradation of Gangtok-Burtuk-Ranka Road [S.Share of NLCPR] Shyam Rai 11.01.06 31.3.06 2004 221.54 12.23 84.28 96.51 125.03 44%  
3 Const. of link road from lower Lingdum to Adampool Km 3rd & 4th, Phase-II( State Share of NABARD) i/c compensation 13.85 Lakhs (Revised) Ajay Rai 16.11.05 15.05.07 Revised 2008 43.49 18.59 19.85 38.44 0.00 100%  
4 Premix Carpetting & Protective work to approch road to cremation ground at Ranipool(NABARD-state share) Praveen Kumar Agrawal 31.01.06 31.3.06 2005 11.14 9.23 1.87 11.10 0.00 100%  
5 upgradation, providing premix carpeting to Tintek Dikchu Road Km 1st to 12th ( State share of NLCPR Scheme)]       2009 383.41 0.00 0.00 0.00 383.41 0%  
      TOTAL EXPANSION NORTH DISTT        818.37 139.69 106.00 245.69 567.59