| DETAILS OF STATE PLAN SCHEMES INDICATING SPILLOVER TO FINANCIAL YEAR 2009-10 | ||||||||||||
| NORTH DISTRICT ( MANGAN SUB-DIVISION & SUB- DIVISION- IV) | ||||||||||||
| MAJOR HEAD :- EXPANSION | (Rupees in lakh) | |||||||||||
| Sl. No | NAME OF WORK | Name of Contractor | Date of Commencement | Due date of Completion | Year of Sanction | Sanctioned Cost | Expenditure | Spillover to 2009-10 | Physical Progress | Remarks | ||
| Upto 2007-08 | During 2008-09 | Total | ||||||||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 |
| b. SUB-DIVISION :- No. IV | ||||||||||||
| 1 | Premix Carpetting on Penlong Tintek Road km 12th to 20th | Suresh Mundra | 28.11.02 | 31.5.06 | 2000 | 158.79 | 99.64 | 0.00 | 99.64 | 59.15 | 66% | |
| 2 | Upgradation of Gangtok-Burtuk-Ranka Road [S.Share of NLCPR] | Shyam Rai | 11.01.06 | 31.3.06 | 2004 | 221.54 | 12.23 | 84.28 | 96.51 | 125.03 | 44% | |
| 3 | Const. of link road from lower Lingdum to Adampool Km 3rd & 4th, Phase-II( State Share of NABARD) i/c compensation 13.85 Lakhs (Revised) | Ajay Rai | 16.11.05 | 15.05.07 | Revised 2008 | 43.49 | 18.59 | 19.85 | 38.44 | 0.00 | 100% | |
| 4 | Premix Carpetting & Protective work to approch road to cremation ground at Ranipool(NABARD-state share) | Praveen Kumar Agrawal | 31.01.06 | 31.3.06 | 2005 | 11.14 | 9.23 | 1.87 | 11.10 | 0.00 | 100% | |
| 5 | upgradation, providing premix carpeting to Tintek Dikchu Road Km 1st to 12th ( State share of NLCPR Scheme)] | 2009 | 383.41 | 0.00 | 0.00 | 0.00 | 383.41 | 0% | ||||
| TOTAL EXPANSION NORTH DISTT | 818.37 | 139.69 | 106.00 | 245.69 | 567.59 | |||||||