DETAILS OF STATE PLAN SCHEMES INDICATING SPILLOVER TO FINANCIAL YEAR  2009-10
NORTH DISTRICT ( MANGAN SUB-DIVISION & SUB- DIVISION- IV)
NEW ROADS              (Rupees in lakh)  
Sl.No NAME OF WORK Name of Contractor Date of Commencement Due date of Completion Year of Sanction Sanctioned Cost Expenditure Spillover to 2009-10 Physical Progress Remarks
As on 31/03/2008 During 2008-09 Total  
1 2 3 4 5 6 7 8 9 10 11 12 13
1 Const. of Link road to Yumi Samdong km 1st & 2nd 37.41and LC 17.07 ( Forest) (state portion of RSVY works) Tshering D. Lachungpa 21.6.04 21.12.05 2004 & 2005 54.48 31.57 21.63 53.20 0.00 100% A/c Closed 
2 Construction of link road from Bay to Pentong in North Sikkim.  (state portion of RSVY works)i/c Comp of 22.52 Lakhs  revised 2008 Bernard Lepcha     Revised 2008 59.97 0.00 24.56 24.56 35.41 80%  
3 Construction of Link road from Takchi phatak to upper luing km 1st to 5th (NABARD) State Share i/c Compensation Tsh. R  Bhutia- &others      2007 32.21 20.90 1.21 22.11 10.10 30%  
4 Const of Link Road from Aho- Mangim  Km 2rd ( Damaged Comp) LRD - - 2008 3.96 0.00 3.96 3.96 0.00 100%  
5 Construction of Link road from 3rd Mile turning of Tintek Dikchu to Raksay via Kedangthang Km  4th to 6th ( State share of NABARD Scheme) I/C lc Rs. 13.66 Lakhs  P.P.Dhakal     2008 64.09 0.00 21.58 21.58 42.51    
6 Protective works to approach Road to JNV Road in phodong North Sikkim        2008-09  37.53 0.00 0.00 0.00 37.53    
7 Const of Link Road from Passingdang PHSC to Lingthem Gumpa and Lingdom Gumpa(NLCPR)        2008-09  484.26 0.00 0.00 0.00 484.26    
  TOTAL  :-  NEW ROADS     736.50 52.47 72.94 125.41 609.81