BORDER AREA DEVELOPMENT PROGRAMME (BADP)

Statement showing quarterly progress (financial) for the quarter ending :March 2008

Name of the State:Sikkim

Name of sector Name of the Scheme/work Location Approved outlay
District Block Village
1 2 3 4 5 6
Infrastructure Bakcha -Labi 2nd km North     50.00
Infrastructure Rongli Talkharka road II phase 3 kms East     100.00
Infrastructure Construction of approach road to Thomche gumpa at Lachung. North     15.69
Infrastructure Construction of new road from gumpa golai to Chanzing,Lachen. North     38.10
Infrastructure Cosntruction of approach road and parking for Gymnasium hall at Chungthang. North     6.92
Infrastructure Upgradation /Strengthening and carpeting of approach road to Latoong village. North     42.79
Infrastructure Construction of Guest house/inspection Bunglow at Yakthang Lachen(Thangu). North     138.00
  Total       391.50