ECONOMIC  IMPORTANCE  &  INTER STATE   CONNECTIVITY   SCHEMES   (ON GOING  SCHEMES)
Sl Name of Scheme Sanctioned Cost Fund Received from GOI Expenditure March-08 Balance Fund to recieve from GOI Physical Progress Funds required                          for  2008-09
0 1 2 3 6 7=(2-6) 8 9
1 Surface Strengthening Protective works & Premix Carpetting of Gyalshing Pelling road in West Sikkim. 87.86 87.86 87.86 0.00 100% 0.00
2 Drainage System & Carpetting of Rimbi Yuksam road, West Sikkim 219.37 219.37 219.37 0.00 100% 0.00
3 Surface Strengthening Protective works & Premix Carpetting of Duga Pacheykhani Road Km1st to 14th in East Sikkim 433.77 433.77 433.77 0.00 87% 0.00
4 Widening, Surface Improvement  Protective works & Drainage along Sirwani Bermoik Phongla Road, South Sikkim 999.08 866.00 766.00 133.08   133.08
5 Surface improvement, protective works Drainage along Rangpo-Duga-Pendam road 950.00 304.23 0.00 645.77 50% 500.00
6 Improvement of Rhenok-Simana Khola Km 1st to 3rd 250.00 50.00 0.00 200.00 5% 100.00
7 Widening, Surface Improvement  Protective works &Carpetting of                   Melli Phongla Road Km 1st - 23rd in South Sikkim 1298.60 0.00 0.00 1298.60 30% 500.00
8 Improvement of Sang Dipudara road  347.74 347.74 0.00 0.00   0.00
9 Improvement of Pakyong Karthak Nayabusty Raigoan road 398.52 160.00 0.00 238.52   238.52
10 Construction of Gurassey road from Bio-Diversity Park (Temi) 1010.92 127.26 0.00 883.66   420.00
11 Construction of road from Rathong to Kimchithang road Km 1st to 15th. 701.89 0.00 0.00 701.89   250.00
  TOTAL 6697.75 2596.23 1507.00 4101.52   2141.60