STATUS OF NEC WORKS UNDER ROADS & BRIDGES DEPARTMENT, GOVERNMENT OF SIKKIM AS ON 31st MARCH 2008 |
||||||||||
| Sl | Name of Scheme | Sanctioned Cost | Fund Received | Expenditure till March-08 | Balance Funds to be recieved from NEC | Physical Progress | Funds required for 2008-09 | Remarks | ||
| from NEC | State | Total | ||||||||
| 0 | 1 | 2 | 3 | 4 | 5 | 6 | 7=(2-3) | 8 | 9 | 10 |
| 1 | Surface Improvement, Drainage & Protective works on Namchi-Rong Road, km 1st to 13th. | 498.60 | 448.74 | 49.86 | 498.60 | 494.12 | 0.00 | 100% | nil | |
| 2 | Replacement of Gour Suspension Bridge over River Teesta on DSM Rd | 443.87 | 289.50 | 32.16 | 321.66 | 321.37 | 109.98 | 92% | 109.98 | |
| 3 | Strengthening,Drainage Carpetting of Sangkalang Bey Sakyong Road to Tingbong High School in North Sikkim. | 401.38 | 280.47 | 31.16 | 311.63 | 316.14 | 80.77 | 100% | 80.77 | |
| 4 | Replacement of Tak Cham Chu Suspension Bridge on GRBA Road | 476.74 | 269.70 | 29.97 | 299.67 | 267.60 | 159.37 | 60% | 159.37 | |
| 5 | Replacement of Sumin Wooden Suspension Bridge on Sang Khola Sumin Road | 285.40 | 209.70 | 23.30 | 233.00 | 231.34 | 47.16 | 100% | 47.16 | |
| 6 | Replacement of Ringyang Suspension Bridge on Soreng Sombaria Rd | 332.02 | 298.70 | 33.19 | 331.89 | 328.94 | 0.12 | 100% | 0.12 | |
| 7 | Const of major retaining structure on app.road to Raj bhawan VIP complex and TNA school | 110.58 | 74.70 | 8.30 | 83.00 | 79.66 | 24.82 | 100% | 24.82 | |
| 8 | Const of 40 mtr span steel bridge over lower Ben khola at Saino Taar along Pabong Yangang road | 137.34 | 194.47 | 21.61 | 216.08 | 206.54 | 70.89 | 100% | 70.89 | |
| 9 | Const of 40 mtr span steel bridge over Rinzi khola at Kholaghari Namchi Vok road. | 157.50 | 85% | |||||||
| 10 | Improvement of Bermoik Legship road. | 449.46 | 150.60 | 16.73 | 167.33 | 167.33 | 253.91 | 80% | ||
| 11 | Support for purchase of Machineries | 376.00 | 376.00 | 0.00 | 376.00 | 376.00 | 0.00 | 100% | 0.00 | |
| 12 | Construction of road from 10th mile Legship-Kewzing road to Tingmoo village Sikkim | 468.29 | 79.70 | 8.86 | 88.56 | 89.89 | 341.76 | 45% | 170.88 | |
| Sl | Name of Scheme | Sanctioned Cost | Fund Received | Expenditure March-08 | Balance Fund to be recieved from NEC | Physical Progress | Funds required for 2008-09 | Remarks | ||
| from NEC | State | Total | ||||||||
| 13 | Const of 25 mtr span steel bridge over Upper Ben khola at ben Tarku Rabongla (GLVC) road | 90.83 | 178.88 | 19.88 | 198.76 | 198.75 | 74.48 | 100% | 74.48 | |
| 14 | Const of 50 mtr steel bridge on approach road to Khedum village | 190.68 | 98% | |||||||
| 15 | Const. of Makha Bridge over river Tista Khola at Tanak on Makha-Lingi-Yangang-Ravangla road. | 495.25 | 44.55 | 4.95 | 49.50 | 30.23 | 401.18 | 5% | 200.59 | |
| 16 | Replacement of suspension bridge with 102 m span steel bridge over Rabi Khola river at 9th km on Melli - Phong road. | 497.30 | 29.70 | 3.30 | 33.00 | 30.52 | 417.87 | 20% | 208.94 | |
| 17 | Improvement of Chakung Khaniserbong road. | 486.36 | 129.70 | 14.41 | 144.11 | 144.11 | 308.02 | 20% | 154.01 | |
| 18 | Upgradation & Ext. of Marchak Tumblabong Road Km 1st-13th | 1023.00 | 299.00 | 33.22 | 332.22 | 339.05 | 621.70 | 45% | 320.00 | |
| 19 | Surface Strengthening i/c Drainage & carpetting of Sombaria Hilley Road | 845.68 | 185.50 | 20.61 | 206.11 | 208.01 | 575.61 | 50% | 285.00 | |
| 20 | Surface Strengthening Drainage & carpetting of Assam Pakyong Road | 750.78 | 263.00 | 29.22 | 292.22 | 298.27 | 412.70 | 55% | 205.00 | |
| 21 | Upgradation i/c Drainage & Carpeting of Ralong Phamtam Rd | 1183.00 | 199.00 | 22.11 | 221.11 | 222.01 | 865.70 | 30% | 400.00 | |
| 22 | Upgradation and Drainage i/c Replacement of 2 bridges on Kimbubotey Sokpey Road in South District. | 1180.89 | 290.00 | 32.22 | 322.22 | 322.22 | 772.80 | 30% | 250.00 | |
| 23 | Construction and imp. of road from Turung to Suminkhor km 1st to 5th. | 358.66 | 50.00 | 5.56 | 55.56 | 50.00 | 272.79 | 40% | 150.00 | |
| TOTAL | 11239.61 | 4341.61 | 440.62 | 4782.23 | 4722.10 | 5811.64 | 2912.00 | |||