STATUS OF NLCPR WORKS UNDER ROADS & BRIDGES DEPARTMENT, GOVERNMENT OF SIKKIM AS ON 31st MARCH 2008 |
|||||||||||
| Sl | Name of Scheme | Sanctioned Cost | Fund Received from GOI | Expenditure March-08 | Balance Fund to recieve from GOI | Physical Progress | Funds required for 2008-09 | Unspend balance | |||
| Grant | Loan | Total | Amount | % | |||||||
| 0 | 1 | 2 | 3 | 4 | 5 | 6 | 7=(2-6) | 8 | 9 | 10 | 11 |
| a | Scheme sanctioned in 2005-06 (1 Bridge) | ||||||||||
| 1 | Const. of Goshkhan Dara Bridge over river Teesta at Singtam,East Sikkim. | 1337.57 | 421.20 | 46.80 | 468.00 | 468.00 | 782.61 | 35% | 500.00 | 0.00 | |
| b. | Schemes sanctioned in 2004-05 (9 works) | ||||||||||
| 1 | Surface Improvement/Widening, Carpetting & Bridge Replacement on Gyalshing-Soreng Road (up to Dentam). | ||||||||||
| a. | Pelling-Dentam road (20 km) & | 200.30 | 1082.55 | 120.28 | 1202.83 | 903.89 | 48.13 | 85% | 48.13 | 298.94 | 24.85% |
| b. | Replacement of existing BB lal suspension Bridge | 1050.66 | 75% | ||||||||
| 2 | Carpetting and surface improvement of Soreng Budang Road via Malbassy Km 1st - 11th. | 339.00 | 305.22 | 33.78 | 339.00 | 339.00 | 0.00 | 100% | 0.00 | 0.00 | |
| 3 | Construction of premix carpetting /imp. Dentam Uttrey road Km 1st to 10th. | 399.00 | 266.00 | 29.56 | 295.56 | 243.92 | 103.44 | 70% | 103.44 | 51.64 | 17.47% |
| 4 | Repalacement of 2 nos existing Suspension bridge by steel bridge on Pelling-Yoksum road.(Rathong & Rimbi) | 327.57 | 287.38 | 31.93 | 319.31 | 262.01 | 8.26 | 45% & 95% | 8.26 | 57.30 | 17.94% |
| 5 | Slope Stabilization of Labing & Chongrang slides on Yoksum Legship road | 127.53 | 110.73 | 12.30 | 123.03 | 123.03 | 4.50 | 100% | 4.50 | 0.00 | |
| 6 | Carpetting and surface improvement of Namchi-Rabongla (26 km) road. | 1207.31 | 1045.88 | 116.21 | 1162.09 | 1164.19 | 45.22 | 90% | 45.22 | -2.10 | |
| 7 | Upgradation, Surface strengthening, drainage & P/W on Ravangla Makha Road 26 kms | 994.00 | 864.64 | 96.07 | 960.71 | 966.98 | 33.29 | 100% | 33.29 | -6.27 | |
| 8 | Upgradation, Gangtok Burtuk Ranka Road, 8 kms in East District | 420.00 | 367.20 | 40.80 | 408.00 | 387.11 | 12.00 | 70% | 12.00 | 20.89 | 5.12% |
| 9 | Const. of diversion road Ranipool-Pakyong road km 1st-3rd. | 236.87 | 204.99 | 22.77 | 227.76 | 170.78 | 9.11 | 50% | 9.11 | 56.98 | 25.02% |
| Total a,b | 5302.24 | 4534.59 | 503.70 | 5038.29 | 4560.91 | 263.95 | 763.95 | ||||