DIVISION :
NORTH |
|
|
|
|
|
|
|
|
|
|
Oct-08 |
|
|
|
|
|
Sl.No |
Name of Schemes |
Name
of Contractor |
Funding
Agency |
SANCTIONED AMOUNT |
Date of Commencement |
Stipulated Date of
Completion |
Physical Progress in % |
Financial
Progress |
Remarks |
|
|
|
|
Total |
C.share |
S.
share |
(Head) |
Expenditure
till date |
|
|
|
|
Total |
S.Share |
C.Share |
Work
Remrks |
Plan |
|
|
|
|
| |
|
CENTRAL SPONSORED
SCHEMES |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1 |
Upgradation
Ranka - Luing-Gangtok-Burthuk-Road Km 14th to 21st |
Mr. Shyam Rai |
NLCPR |
641.54 |
420.00 |
221.54 |
Expansion |
11-Jan-05 |
19-Jul-07 |
68% |
399.34 |
12.23 |
387.11 |
work in
progress |
Tenth Plan |
Spill Over Acct |
|
|
|
|
2 |
Construction
0f 90m span steel bridge over Takcham Chu along C.R.B.A Road, Km 21st |
Mrs. Meera Rai |
NEC |
476.74 |
476.74 |
0.00 |
Expansion |
9-Jan-06 |
8-Oct-06 |
94% |
267.60 |
0.00 |
267.60 |
work in
progress |
Tenth Plan |
Spill Over Acct |
|
|
|
|
3 |
Upgradation /
carpeting & extension i/c providing drainage and protective works of
Marchak - Tumlabong road, Km 1st to 13th in East Sikkim |
M/s Ladakhi
Const. Pvt. Ltd. |
NEC |
1,023.00 |
1,023.00 |
0.00 |
Expansion |
9-Nov-06 |
18-May-08 |
58% |
339.05 |
0.00 |
339.05 |
work in
progress |
Tenth Plan |
Spill Over Acct |
|
|
|
|
4 |
Construction
of steel bridge over Teesta river at Gour |
Mr. Samdup
Lepcha |
NEC |
488.57 |
488.57 |
0.00 |
NEC |
21-Jan-06 |
22-Jan-07 |
92% |
321.37 |
0.00 |
321.37 |
In Progress |
Tenth Plan |
Spill Over Acct |
MPR |
|
|
|
5 |
Strengthening
/ drainage carpetting of SBS road to Tingbong high school |
Mr. G.N.
Agarwal |
NEC |
447.74 |
401.37 |
46.37 |
NEC |
29-Apr-05 |
30-Apr-06 |
100% |
316.14 |
0.00 |
316.14 |
Completed |
Tenth Plan |
Spill Over Acct |
MPR |
|
|
|
6 |
Construction
of Steel Bridge on Approach road to Khedum Village in North Sikkim. |
Mr. Penzong
Lachungpa |
NEC |
190.68 |
190.68 |
0.00 |
NEC |
24-Feb-06 |
23-Jan-07 |
94% |
116.98 |
0.00 |
116.98 |
In Progress |
Tenth Plan |
Spill Over Acct |
MPR |
|
|
|
7 |
Upgradation
& Surface strengthening of Ranka-Sichey road Km 1st to 3rd |
Mr. Rajesh
Agarwal |
CRF |
119.05 |
88.26 |
30.79 |
Removal |
17-Mar-05 |
31-May-06 |
100% |
31.03 |
0.00 |
31.03 |
Final
Payment to be made |
Tenth Plan |
Both |
Sub Div - IV |
|
|
|
8 |
Upgradation of
Phodong -Labrang Gumpa |
Mr. K.N. Bhutia |
CRF |
158.96 |
158.96 |
0.00 |
CRF |
3-Nov-05 |
2-Oct-06 |
100% |
118.77 |
0.00 |
118.77 |
Completed |
Tenth Plan |
Spill Over Acct |
MPR |
|
|
|
9 |
Construction
of 18 mtrs span Steel Bridge over Rakshey Khola along Penlong - Tintek road
at Km 13yh, CH: 1 |
- |
CRF |
90.99 |
90.99 |
0.00 |
CRF |
18-Oct-06 |
- |
90% |
35.97 |
0.00 |
35.97 |
work in
progress |
Tenth Plan |
Not in Both |
|
|
|
|
10 |
Construction
of app. Road to Thomchi Gumpa. |
Mr. Tashi
Lachungpa |
BADP |
15.69 |
0.00 |
15.69 |
BADP |
6-Feb-07 |
5-May-07 |
10% |
10.00 |
0.00 |
10.00 |
Completed |
Tenth Plan |
Spill Over Acct |
MPR |
|
|
|
11 |
Construction
of new road from Gumpa Golai to Chanzing, Lachen. |
Mr Nangden
Lachungpa |
BADP |
38.10 |
38.10 |
0.00 |
BADP |
- |
- |
- |
0.00 |
0.00 |
0.00 |
work in
progress |
|
Spill Over Acct |
MPR |
|
|
|
12 |
Construction
of approach road and parking for Gymnasium hall at Chungthang. |
|
BADP |
6.92 |
6.92 |
0.00 |
BADP |
- |
- |
- |
0.00 |
0.00 |
0.00 |
- |
|
Not in Both |
MPR |
|
|
|
13 |
Upgradation
/ Strengthening and Carpeting of approach road to Latoong Village. |
Mr
Nangden Lachungpa |
BADP |
42.79 |
42.79 |
0.00 |
BADP |
- |
- |
70% |
0.00 |
0.00 |
0.00 |
work
in progress |
|
Spill Over Acct |
MPR |
|
|
|
14 |
Construction
of Guest House / Inspection Bunglow at Yakthang, Lachen (Thangu). |
|
BADP |
138.00 |
138.00 |
0.00 |
BADP |
- |
- |
- |
0.00 |
0.00 |
0.00 |
- |
|
Not in Both |
|
|
|
|
15 |
Extension of
Bakcha -Labi road Km 3rd & 4th. State share of BADP land compansation. |
Mr. Ugen Nedup
Bhutia |
BADP |
0.00 |
0.00 |
0.00 |
BADP |
- |
- |
100% |
0.00 |
0.00 |
0.00 |
Forest
compansation to be paid |
|
|
MPR |
|
|
|
16 |
Construction
of approach road to Thomchi Gumpa. |
|
BADP |
5.00 |
5.00 |
0.00 |
BADP |
- |
- |
10% |
0.00 |
0.00 |
0.00 |
|
|
|
|
|
|
|
17 |
Construction
of Link Road from Zimchung to Nampathang KM 1st to 3rd |
Mr. Zingmee
Ongda, Mr. Dawa.Lepcha, Mr. Choppel Tshering |
RSVY |
112.11 |
112.11 |
0.00 |
RSVY |
10-Nov-05 |
10-Nov-06 |
100% |
112.11 |
0.00 |
112.11 |
Completed |
Tenth Plan |
Spill Over Acct |
|
|
|
|
18 |
Construction
of Link Road from 3rd Mile Turning of Tintek Dikchu road to Rakshey via
Kedhangthang. Km 1st to 3rd. |
Punya Prasad
Dhakhal |
RSVY |
143.79 |
121.79 |
22.00 |
New Road |
21-Oct-05 |
31-Jan-07 |
100% |
120.76 |
0.00 |
120.76 |
work in
progress |
Tenth Plan |
Spill Over Acct |
|
|
|
|
19 |
Construvction
of Link Road from Bay to Pentong in North Sikkim. |
Mr. Bernald
Lepcha |
RSVY |
187.45 |
150.00 |
37.45 |
New Road |
22-Sep-05 |
21-Aug-06 |
65% |
128.03 |
0.00 |
128.03 |
In Progress |
Tenth Plan |
Spill Over Acct |
MPR |
|
|
|
20 |
Upgradation
carpetting works of Chaten Khimten Village road in North Sikkim |
Mr. Janam
Lachen |
RSVY |
38.00 |
38.00 |
0.00 |
RSVY |
12-Sep-05 |
11-Aug-06 |
100% |
38.00 |
0.00 |
38.00 |
Completed |
Tenth Plan |
Not in Both |
|
|
|
|
21 |
Construction
of Heli Port at Lachung |
Mr. Nidup
Lachungpa |
CSS |
38.89 |
0.00 |
38.89 |
Tourism-800-Others
Exp-78(P) |
3-Apr-00 |
2-Jan-01 |
75% |
28.43 |
0.00 |
28.43 |
Defence
clearance not yet received |
Ninth Plan |
Spill Over Acct |
|
|
|
|
22 |
Protective
Drainage and Carpetting works on SBS Road Km 3 & 4 |
Mr. Pintso
Namgyal |
Central plan
Scheme |
27.19 |
27.19 |
0.00 |
- |
27-Nov-01 |
26-Feb-02 |
100% |
19.37 |
0.00 |
19.37 |
Completed |
Ninth Plan |
|
|
|
|
|
23 |
Protective
Drainage and Carpetting works on SBS Road Km 5 & 6 |
Mr. Karma
Lepcha |
Central plan
Scheme |
23.38 |
23.38 |
0.00 |
- |
11-Jan-03 |
10-Oct-03 |
100% |
16.77 |
0.00 |
16.77 |
Completed |
Ninth Plan |
|
|
|
|
|
24 |
Protective
Drainage and Carpetting works on SBS Road Km 7 |
Mr.
Ten Tsh. Lepcha |
Central
plan Scheme |
11.17 |
11.17 |
0.00 |
- |
27-Nov-01 |
26-Nov-02 |
100% |
7.17 |
0.00 |
7.17 |
Completed |
Ninth
Plan |
|
|
|
|
|
25 |
Protective
Drainage and Carpetting works on SBS Road Km 8 |
Mr. Dupden
Lepcha |
Central plan
Scheme |
22.48 |
22.48 |
0.00 |
- |
27-Nov-01 |
27-Nov-02 |
100% |
19.28 |
0.00 |
19.28 |
Completed |
Ninth Plan |
|
|
|
|
|
26 |
Protective
Drainage and Carpetting works on SBS Road Km 9 |
Mr.
Pintso Lepcha |
Central
plan Scheme |
19.23 |
19.23 |
0.00 |
- |
27-Nov-01 |
28-Nov-02 |
100% |
18.21 |
0.00 |
18.21 |
Completed |
Ninth
Plan |
|
|
|
|
|
27 |
Widening of
upgradation, carpetting, protective of drainage wors on approach road to
Zimchung Busty from DAC road, Mangan |
Department. |
MP (LAPS) |
25.00 |
25.00 |
0.00 |
- |
- |
- |
100% |
0.00 |
0.00 |
0.00 |
In Progress |
|
Spill Over Acct |
MPR |
|
|
|
28 |
Construction
of road from lower Lingdum to
Adampool, Km 3rd & 4th |
Mr. Ajay Rai |
NABARD |
103.07 |
73.43 |
29.64 |
Expansion |
16-Nov-06 |
15-May-07 |
80% |
92.02 |
18.59 |
73.43 |
In Progress |
Tenth Plan |
Not in Both |
|
|
|
|
29 |
Carpetting of
app. Road to Crematorium ground at Jalipool. |
Mr. Praveen
Agarwal |
NABARD |
31.80 |
20.66 |
11.14 |
Expansion |
31-Jan-06 |
15-Jun-06 |
100% |
30.01 |
9.35 |
20.66 |
Final
Payment to be made |
Tenth Plan |
Both |
MPR |
|
|
|
30 |
Construction
of Link Road from Takchi Phatak to Upper Luing, Km 1st |
Mr. Tsweang
Rinzing Bhutia |
|
322.84 |
289.93 |
32.910 |
New Road |
18-Aug-05 |
17-Aug-06 |
|
70.72 |
20.90 |
49.82 |
work in
progress |
Tenth Plan |
Both |
|
|
|
|
31 |
Construction
of Link Road from Takchi Phatak to Upper Luing, Km 2 nd |
Dewjang Bhutia |
NABARD |
New Road |
18-Aug-05 |
17-Aug-06 |
5% |
Work just
started |
Tenth Plan |
Both |
|
|
|
|
32 |
Construction
of Link Road from Takchi Phatak to Upper Luing, Km 3rd |
Tempo Gyatso
Bhutia |
NABARD |
New Road |
23-Sep-05 |
22-Sep-06 |
25% |
Work just
started |
Tenth Plan |
Both |
|
|
|
|
33 |
Construction
of Link Road from Takchi Phatak to Upper Luing, Km 4th |
Yangchen Dolma
Bhutia |
NABARD |
New Road |
23-Sep-05 |
22-Sep-06 |
0% |
work in
progress |
Tenth Plan |
Both |
|
|
|
|
34 |
Construction
of Link Road from Takchi Phatak to Upper Luing, Km 5th |
Yangchen Dolma
Bhutia |
NABARD |
New Road |
23-Sep-05 |
22-Sep-06 |
0% |
work in
progress |
Tenth Plan |
Both |
|
|
|
|
|
WORKS SANCTIONED
UNDER STATE PLAN |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
35 |
Surface
renewal / restoration works on approach road to Mission Khoti. |
Mr. Ugen palzor |
State Plan |
32.79 |
0.00 |
32.79 |
Removal |
28-Feb-04 |
27-Aug-04 |
100% |
32.60 |
32.60 |
0.00 |
Final Payment |
Tenth Plan |
MPR |
Magan |
|
|
|
36 |
Premix
carpetting p/w approach road to Hee-Gyathang School. |
Department. |
State Plan |
23.01 |
0.00 |
23.01 |
Removal |
- |
- |
100% |
19.99 |
19.99 |
0.00 |
Completed |
|
MPR |
Magan |
MPR |
|
|
37 |
Premix
carpeting on GRBA road KM 1st -10th (Phase I ) Revised |
Mr. A.N. Upreti |
State Plan |
215.65 |
0.00 |
215.65 |
Removal |
13-Jan-03 |
12-Jul-04 |
96% |
207.01 |
207.01 |
0.00 |
work in
progress |
Tenth Plan |
MPR |
Sub Div - IV |
MPR |
|
|
38 |
Premix
carpetting, improvement of GRBA road Km 18th to 21st and Assam Pakyong Road
Km 1st to 6th. |
Mr. Amrit Rai |
State Plan |
254.76 |
0.00 |
254.76 |
Removal |
25-Aug-04 |
31-Mar-06 |
100% |
184.20 |
184.20 |
0.00 |
Final
Payment to be made |
Tenth Plan |
Both |
Sub Div - IV |
MPR |
|
|
39 |
Uplifting
& Surface & Drainage works, improvement along approach road to Sichey
school. |
Mr.
Rohit Pradhan |
State
Plan |
3.77 |
0.00 |
3.77 |
Removal |
27-Feb-06 |
29-Dec-06 |
100% |
0.00 |
3.03 |
0.00 |
Final
Payment to be made |
Tenth
Plan |
MPR |
Sub Div - IV |
|
|
|
40 |
Upgradation
& Surface strengthening of Ranka-Sichey road Km 1st to 3rd |
Mr. Rajesh
Agarwal |
CRF |
119.05 |
88.26 |
30.79 |
Removal |
17-Mar-05 |
31-May-06 |
100% |
31.03 |
0.00 |
31.03 |
Final
Payment to be made |
Tenth Plan |
Both |
Sub Div - IV |
|
|
|
41 |
Upgradation of
Marchak Tumlabong Road (NEC ) State Share for LC |
Compensatiion |
State Plan |
100.00 |
0.00 |
100.00 |
Removal |
- |
- |
37% |
37.00 |
37.00 |
0.00 |
work in
progress |
|
MPR |
Sub Div - IV |
|
|
|
42 |
Upgradation
and Imp of Rumtek Ranka road Km 18th |
Department. |
State Plan |
1.36 |
0.00 |
1.36 |
Removal |
- |
- |
0% |
0.00 |
0.00 |
0.00 |
work in
progress |
|
MPR |
Sub Div - IV |
|
|
|
43 |
Construction
of 15 mtrs span RCCl Bridge over Khedum Chu |
Gyatso Bhutia |
State Plan |
20.72 |
0.00 |
20.72 |
Removal |
12-Nov-98 |
11-Mar-99 |
100% |
19.36 |
19.36 |
0.00 |
|
Ninth Plan |
Not in Both |
Magan |
|
|
|
44 |
Land
Compensation for the work construction of Multi Span Bridge over River Teesta
at Gour at Dzongu |
LC |
State Plan |
6.84 |
0.00 |
6.84 |
Removal |
- |
- |
100% |
6.62 |
6.62 |
0.00 |
|
|
Not in Both |
Magan |
|
|
|
45 |
Construction
of 55m Supension Bridge over Khedumcu at Lachung |
Needup Lacungpa |
State Plan |
112.31 |
0.00 |
112.31 |
Removal |
12-Nov-98 |
11-Jul-99 |
100% |
100.09 |
100.09 |
0.00 |
Copansation
Remaining |
Ninth Plan |
Not in Both |
Magan |
|
|
|
46 |
Premix
carpetting,on Penlong - Tintek road Km 12th - 20th |
Mr. Suresh
Mundra |
State Plan |
158.79 |
0.00 |
158.79 |
Expansion |
28-Nov-02 |
31-Mar-06 |
100% |
99.64 |
99.64 |
0.00 |
Final bill to
be paid |
Tenth Plan |
Both |
Magan |
|
|
|
47 |
Upgradation
Ranka - Luing-Gangtok-Burthuk-Road Km 14th to 21st |
Mr. Shyam Rai |
NLCPR |
641.54 |
420.00 |
221.54 |
Expansion |
11-Jan-05 |
19-Jul-07 |
68% |
399.34 |
12.23 |
387.11 |
work in
progress |
Tenth Plan |
Spill Over Acct |
|
|
|
|
48 |
Construction
of road from lower Lingdum to
Adampool, Km 3rd & 4th |
Mr. Ajay Rai |
NABARD |
103.07 |
73.43 |
29.64 |
Expansion |
16-Nov-06 |
15-May-07 |
80% |
92.02 |
18.59 |
73.43 |
In Progress |
Tenth Plan |
Not in Both |
|
|
|
|
49 |
Carpetting of
app. Road to Crematorium ground at Jalipool. |
Mr. Praveen
Agarwal |
NABARD |
31.80 |
20.66 |
11.14 |
Expansion |
31-Jan-06 |
15-Jun-06 |
100% |
30.01 |
9.35 |
20.66 |
Final
Payment to be made |
Tenth Plan |
Both |
|
|
|
|
50 |
Adjustment of
STCS bill for the work Carpeting at Chandey Golai |
- |
State Plan |
- |
- |
- |
Expansion |
- |
- |
100% |
0.50 |
0.50 |
0.00 |
- |
|
Not in Both |
|
|
|
|
51 |
Const. of GOR
Santok road Km. 1st |
Mr.Pentok
Lepcha |
State Plan |
29.76 |
0.00 |
29.76 |
Expansion |
|
|
100% |
21.61 |
21.61 |
0.00 |
Completed |
|
Not in Both |
|
|
|
|
52 |
Construction
of link road to Aho - Manghim Km 1st |
Mr. B.K. Upreti |
State Plan |
16.88 |
0.00 |
16.88 |
Link Road |
2-Dec-04 |
15-Jan-07 |
94% |
11.37 |
11.37 |
0.00 |
work in
progress |
Tenth Plan |
|
|
|
|
|
53 |
Const. of link
road to Aho - Manghim Km 2nd |
Mr. K. Vijayan |
State Plan |
18.88 |
0.00 |
18.88 |
Link Road |
2-Dec-04 |
15-Jan-07 |
20% |
|
|
|
delayed due to
land compensation |
Tenth Plan |
|
|
|
|
|
54 |
Const. of link
road to Aho - Manghim Km 3 rd |
Mr. K. Vijayan |
State Plan |
19.27 |
0.00 |
19.27 |
Link Road |
1-Dec-04 |
15-Jan-07 |
2% |
|
|
|
work in
progress |
Tenth Plan |
|
|
|
|
|
55 |
Construction
of app. Road from Samdong Cha Chu to Yumi Samdong, north Sikkim. Km 1st &
2nd |
Mr. T. Doma
Lachungpa |
State Plan |
54.48 |
0.00 |
54.48 |
New Road |
21-Jun-04 |
20-Dec-05 |
36% |
31.57 |
31.57 |
0.00 |
In Progress |
Tenth Plan |
Both |
|
|
|
|
56 |
Construction
of Rest House at Samdong in East Sikkim. |
Mr. Nitup
Lepcha |
Addl.Facilities |
78.70 |
0.00 |
78.70 |
Addl.Facilities |
20-May-03 |
19-Apr-04 |
100% |
75.44 |
75.44 |
0.00 |
Completed,
Final bill paid |
Tenth Plan |
Both |
|
|
|
|
57 |
Approach Road
to Samdong Rest House at Samdong East Sikkim |
Mr. Dorjee
Choppel |
State Plan |
14.04 |
0.00 |
14.04 |
Addl.Facilities |
20-May-03 |
19-Apr-04 |
100% |
14.04 |
14.04 |
0.00 |
Completed |
Tenth Plan |
|
|
|
|
|
58 |
Upgradation,carpetting,
protective and drainage of SBS road to Lingtam PHSE Km 1st to 5th. |
Mr. Samdup
Lepcha |
State Plan |
385.54 |
0.00 |
385.54 |
Strengthning
Road Infrastructure |
- |
- |
20% |
42.22 |
42.22 |
0.00 |
work in
progress |
|
Spill Over Acct |
MPR |
|
|
|
59 |
Upgradation,carpetting,
protective and drainage works of DSM road to Gour School Km 1st to 8th. |
Mr. Soden
Gyamptso Bhutia |
State Plan |
391.66 |
0.00 |
391.66 |
Strengthning
Road Infrastructure |
1-Jun-08 |
1-Jan-09 |
25% |
57.78 |
57.78 |
0.00 |
work in
progress |
Eleventh Plan |
|
MPR |
|
|
|
60 |
Extension of
Link Road from Gangtok-Rumtek-Sang Road Km 12th Ch: 7 to Tatopani Rumtek
Road. |
- |
State Plan |
10.05 |
0.00 |
10.05 |
Link Road |
2007 |
- |
5% |
0.00 |
0.00 |
0.00 |
work in
progress |
Tenth Plan |
|
|
|
|
|
61 |
Additional
sanction for Land Comensation for the work ' Construction of Link Road Km 1st
to 3rd from Ranipool-Pakyong Road to Mangheem at Aho. |
Land Compensation |
State Plan |
42.02 |
0.00 |
42.02 |
Link Road |
2007 |
- |
- |
25.00 |
25.00 |
0.00 |
- |
Tenth Plan |
|
|
|
|
|
62 |
Construction
of Rest House at Samdong in East Sikkim. |
Mr. Nitup
Lepcha |
Addl.Facilities |
78.70 |
0.00 |
78.70 |
Addl.Facilities |
20-May-03 |
19-Apr-04 |
100% |
75.44 |
75.44 |
0.00 |
Completed,
Final bill paid |
Tenth Plan |
Both |
|
|
|
|
63 |
Construction
of Guest House at Pentok, Mangan, North Sikkim. |
- |
Addl.Facilities |
187.08 |
0.00 |
187.08 |
Addl.Facilities |
2006 |
- |
- |
0.00 |
0.00 |
0.00 |
|
Tenth Plan |
MPR |
|
|
|
|
64 |
Premix
Carpetting imp & widening of D.S.M road km 1st -8th |
Songden Gyamtso
Bhutia |
State Plan |
391.66 |
0.00 |
391.66 |
Strengthening
Road Infrastructure In Dzongu |
1-Feb-08 |
1-Jan-09 |
26% |
57.78 |
57.78 |
0.00 |
work in
progress |
Eleventh Plan |
|
|
Earlier it was at expansion |
MPR |
|
65 |
Strengthening
Carpeting and P/W on Lingtam to Lindem Road Km 1st-5th |
Samdup Lepcha |
State Plan |
385.54 |
0.00 |
385.54 |
Strengthening
Road Infrastructure In Dzongu |
- |
- |
11% |
42.22 |
42.22 |
0.00 |
work in
progress |
Tenth Plan |
|
|
|
|
|
66 |
Widening
protective work drainage & carpetting work on S.B.S Road Km 10th |
Mr. Lobzang
Lepcha |
State Plan |
17.11 |
0.00 |
17.11 |
TSP |
15-Nov-03 |
14-Aug-04 |
73% |
6.36 |
6.36 |
0.00 |
Carpetting work
to be done. |
Tenth Plan |
Spill Over Acct |
MPR |
|
|
|
67 |
Widening
protective work drainage & carpetting work on S.B.S Road Km 12th |
" |
State Plan |
18.86 |
0.00 |
18.86 |
TSP |
15-Nov-03 |
14-Aug-04 |
72% |
8.63 |
8.63 |
0.00 |
Carpetting work
to be done. |
Tenth Plan |
Spill Over Acct |
MPR |
|
|
|
68 |
Widening
protective work drainage & carpetting work on S.B.S Road Km 13th |
Mr. Sonam
Dorjee |
State Plan |
18.86 |
0.00 |
18.86 |
TSP |
18-Nov-04 |