DETAILS OF STATE PLAN SCHEMES INDICATING SPILLOVER BALANCES AS ON 01.04.2007( FINANCIAL YEAR  2007-08)
NORTH DISTRICT ( MANGAN SUB-DIVISION & SUB- DIVISION- IV)
A.    MAJOR HEAD :- 5054-04-04.337-60-47-60.47.71 - Removal (Plan)         ( RUPEES IN LAKHS)       
Sl. NAME OF WORK Name of Contractor Date of Due date of Year of Sanction Sanctioned Cost Total Expenditure Spillover Physical  
Commencement Completion 2007-08 Progress Remarks
A B C D E F G H I J K
                     
1 Widening, Protective work, drainage & Carpetting work on SBS road km 10th  ( 10% above)                  
                   
  (Lobzang Lepcha) 15.11.03 31-5-06 2003 17.11 6.36 10.75 73% Work under progress 
2 Widening, Protective work, drainage & Carpetting work on SBS road km 12th  ( 10% above)                  
                   
  (Lobzang Lepcha) 15.11.03 31-5-06 2003 17.40 8.63 8.77 72% Work under progress 
3 Widening, Protective work, drainage & Carpetting work on SBS road km 13th  ( 10% above)                  
                   
  (Sonam Dorjee Lepcha) 18.11.04 31-5-06 2003 18.86 0.73 18.13 69% Work under progress 
4 Widening, Protective work, drainage & Carpetting work on SBS road km 14th  ( 10% above)                  
                   
  (Topnan Lepcha) 11.01.03 31-5-06 2003 19.76 10.24 9.52 67% Work under progress 
5 Widening, Protective work, drainage & Carpetting work on SBS road km 15th  ( 10% above)                  
                   
  (Topnam Lepcha) 11.01.03 31-5-06 2003 15.35 0.00 15.35 70% Work under progress 
6 Restoration work/ Surface renewal on approach road to Mission Kothi, Mangan                  
  Ugen Palzor Kazi 11.01.03 31-5-06 2003 32.79 29.73 3.06 100% Work A/ c  to be Closed 
7 Premix Carpeting PW drainage on approach road to Hee Gyathang School Deptt     2005 23.01 4.94 18.07 100% Work A/ c  to be Closed 
  (a) Removal Mangan Sub Division   Sub Total      144.28 60.63 83.65    
  SUB - Div IV                  
8 Premixed carpetting on GRS Road km 1st - 4th (13% below)                  
(Phurba Bhutia) 30-05-03 completed 2003 64.41 47.51 16.90 100% Work A/ c  to be Closed 
9 Premix Carpetting on Penlong Tintek Road km 1st to 9th                  
Mohan Bajaj 13.01.03 completed 2003 160.01 130.93 29.08 100% Work A/ c  to be Closed 
10 Premix carpetting on GRBA road Km 1st to 10th. [Phase I] REVISED Shri A.N. Upprety 13/01/03 12/7/2004 2003 215.65 188.16 27.49 100% Work A/ c  to be Closed 
11 Premix carpetting on GRBA road Km 18-21,Assam Pakyong 1st-6th.                        [Phase II] REVISED Shri Amrit Rai