| Division : SOUTH | |||||||||||
| Sl.No | NAME OF WORK | Name of Contractor | Date of Commencement | Date of Completion | Year of Sanction | Sanctioned Cost | Expenditure | Spill over 2007-08 | Physical Progress | ||
| Till 31/03/2006 | During 2006-07 | Total | |||||||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
| III | EXPANSION | ||||||||||
| 1 | Construction of approach Road to Precision Factory at Boomtar, Namchi.[9th plan] | M.P.Agarwal | 1999-2000 | 20.83 | 14.14 | 6.69 | 20.83 | 0.00 | 100% | ||
| 2 | Diversion on Vok-Namchi road at Kamrang College Complex.[9th plan] | M.P.Agarwal | 1999-2000 | 12.15 | 9.60 | 2.55 | 12.15 | 0.00 | 100% | ||
| 3 | Carpetting of Namchi Rong-Sumbuk road Km 1st to 3rd (Soling metalling & Carpetting). [9th plan] | P.K.Agarwal(km1st), Roshan Agarwal(km2nd), Anjani Kr Ararwal(km3rd) | 2000-2001 | 64.18 | 53.00 | 0.00 | 53.00 | 11.18 | 100% | ||
| 4 | Construction of Melli-Turuk Belling link road. [9th plan] | Tej Man Rai | 1997-98 | 8.50 | 6.15 | 2.35 | 8.50 | 0.00 | 100% | ||
| 5 | Construction of road from Gurpisey to Phalidara. Km 1st & 2nd. | Chung Chung Bhutia | 1999-2000 | 50.32 | 35.61 | 0.00 | 35.61 | 14.71 | 100% | ||
| 6 | Drainage works on Yangang - Rangang road Km 1st to Km 2nd | S.B.Chamling | 16/02/03 | 31/03/05 | 2002-03 | 39.32 | 34.42 | 1.32 | 35.74 | 3.58 | 86% |
| 7 | Carpetting, drainage & Protective Works onYangang- Rangang road form Bifurcation Point Km 1st. | S.B.Chamling | 16/02/03 | 31/03/05 | 2002-03 | 15.96 | 9.57 | 0.00 | 9.57 | 6.39 | 100% |
| 8 | Carpetting, drainage & Protective Works on Yangang-Rangang road form Bifurcation Point Km 2nd. | S.B.Chamling | 16/02/03 | 31/03/05 | 2002-03 | 21.84 | 13.16 | 4.54 | 17.70 | 4.14 | 95% |
| 9 | Premix carpetting, Strengthening of Manpur Sumbuk-Rong road Km 5th to 18th.[Add.Sanction 27.74 lakh] | Dependra Rai | 2002-03 | 210.79 | 202.00 | 0.00 | 202.00 | 8.79 | 100% | ||
| 10 | Premix carpetting, drainage & Protective Works on Melli-Turuk -Sadam-Bhanjyang road 1st-17th Km. | Tej Man Rai, Birbal Subba & Rup Narayan Rai | 2002-03 | 290.49 | 255.34 | 4.00 | 259.34 | 31.15 | 85% | ||
| 11 | Construction of Bye Pass from Agam Singh Path Damthang Km1st-3rd. ((LC= Rs 105.00 lakh) | Bhupal Chamling | 18/03/04 | 18/03/05 | 2004-05 | 192.35 | 42.11 | 16.00 | 58.11 | 134.24 | 100% |
| 12 | Surface Improvement of Approach Road to Rock Garden from Debrong Golai-Namchi-Damthang road Km 1st & 2nd. | Dikila Bhutia | 18/03/04 | 18/03/05 | 2004-05 | 70.22 | 45.92 | 10.00 | 55.92 | 14.30 | 100% |
| 13 | Premix carpetting, drainage & Protective works & widening of Sikkip-Vok road (State Share). | Sharkar Agarwal | 15/12/03 | 30/03/06 | 2002-03 | 153.94 | 50.00 | 26.00 | 76.00 | 77.94 | 100% |
| 14 | Premix carpetting, drainage & P/works work on Yangang Makha road Km 1st-21st [S.Share of NLCPR] [Revised] | Passang Lepcha | Completed | 54.13 | 0.00 | 45.00 | 45.00 | 9.13 | 100% | ||
| 15 | Premix carpetting on Rabongla Zarrong road km 1st-11th. | Shreekishan Agarwal | 2002-03 | 354.79 | 231.98 | 38.00 | 269.98 | 84.81 | 100% | ||
| 16 | Construction of link road Rangang road-Yang Yang Makha via Mazuwa Gaon, 3 kms [88.30 + 9.49 (LC)] | Santa Bdr. Chamling, Nar Bdr. Gurung | 6/6/2005 | 6/9/2006 | 2004-05 | 97.79 | 25.36 | 32.96 | 58.32 | 39.47 | 85% |
| 17 | Providing premix carpetting on Approach road & Yard to Palchen Choling Monastry [New Gumpa] at Ralang | Departmental | 18/06/05 | 18/12/05 | 2005-06 | 14.65 | 0.00 | 12.13 | 12.13 | 2.52 | 100% |
| 18 | Shifting of water Pipe lines failing along the alignment of Debrong Golai to Rock Garden at Namchi | 2005-06 | 4.56 | 0.00 | 4.51 | 4.51 | 0.05 | 100% | |||
| 19 | Damthang Chemchey Road | Land Compensation | 2005-06 | 3.50 | 0.00 | 0.00 | 3.50 | 0.00 | |||
| 20 | Restoration work on Namchi-Phong km. 3rd ch. 30 South Sikkim. | Departmental | 2005-06 | 2.90 | |||||||