Road Conditions


Date: 07-May-2021 (09.26 AM)

Maintainance people have been deputed for clearance of minor slips and boulders coming to roads along Phongla-Mamring road above Mamring.

 

Date: 04-May-2021 (10.04 AM)

Namchi to Jorethang Road block at 13km and 17km due to heavy rainfall last night.

Carpeting works along Malbasey Budang road completed today

 

 

Date: 03-May-2021 (02.57 PM)

All most ready for Raft concreting tommrow of both A1 & A2 at Kali khola 55m span steel bridge in South Sikkim.

 

Date: 25-April-2021 (01.35 PM)

Carpeting work along Lower Lingee to Middle Lingee Road under Yangang Sub Division.

 

Date: 23-April-2021 (02.23 PM)

Carpeting  works along Rong Sumbuk road is under progress.

Carpeting along Namchi Phongla road.

 

Date: 20-April-2021 (06.22 PM)

DGBM under progress at Salangdang along Bojeck diversion road.

 

Date: 19-April-2021 (06.19 PM)

Premix carpeting work at Anden Gumpa to Taraybhir road under progress.

 

Date: 19-April-2021 (10.33 AM)

The culvert and cross drainage constructed along Bhanjyang road.

 

Date: 18-April-2021 (11.06 AM)

Laying of 20mm thick premix carpeting at km-2 along Polok Hot-spring road under Rabong Sub-division in South Sikkim.

 

Date: 17-April-2021 (01.56 PM)

Melli Tarey bhir road block at Tarey bhir slide zone km 6th , the machine mobizing to make trafficable .

 

Date: 15-April-2021 (09.42 AM)

Work for carpeting of Palum Syamdas road started today after completion of all sub surface works.

 

Date: 13-April-2021 (11.27 AM)

Carpeting work along Zhapzapay Pakkigaon road in progress.

 

Date: 09-April-2021 (05.56 PM)

Wok to Umrangfalls road now trafficable for all kind of vehicle .

 

Date: 08-April-2021 (11.48 AM)

Laying of flexible pavement 1st layer 60mm dbm is being laid along Ralay Kambal Samdong road ,proper thickness and edge line is being maintained.

 

Date: 06-April-2021 (04.03 PM)

Casting of slab at Dak Banglow complex under Soreng Sub Division.

 

Date: 05-April-2021 (10.29 AM)

Visit of Bojeck diversion road by Secretary NEC along with CE Sir,ACE and other officers of West district.

 

 

Date: 04-April-2021 (06.49 PM)

Arrival of Secretary NEC and team along with Secretary Sir and other officials of R&B at Baiguney Resort.

 

Date: 03-April-2021 (04.06 PM)

Sunk down area after completion of filling work and providing and laying protective work along Magitar to Compound road in South Sikkim.

 

 

Date: 29-March-2021 (11.11 AM)

Flag hoisting ceremony in presence of Hon'ble Governor Shri Ganga Prasad and Hon'ble Chief minister Shri Prem Singh Tamang (Golay)at M.G Marg concluded.

 

Date: 27-March-2021 (05.56 PM)

Temporary road open at Famrong.

 

Date: 18-March-2021 (02.10 PM)

Carpeting started along kholaghari to Jaubari,km 8th to 12th.

 

A1 side erection in progress and A2 side mud cleaning Kayem 2 lane bridge in Dzongu.

 

 

Date: 17-March-2021 (10.06 AM)

Carpeting of Rong Sumbuk road in progress.

 

Date: 15-March-2021 (05.51 PM)

Carpeting of road in DBM is under progress along Phongla Bermiok road.

 

Date: 14-March-2021 (07.10 AM)

RCC culvert at Lingkhim khola along Bojeck diversion the RCC slab which is casted yesterday damaged totally due to heavy flash flood.

 

Date: 13-March-2021 (01.06 PM)

Visit of Dak banglow site by Hon'ble Area MLA Soreng, CE Sir (S/W), DE sir, Architecture team from Gangtok .The work is in progress.

Site inspection by CE Sir along Soreng Malbasey Budang road. Laying of BC is in progress.

 

 

Date: 11-March-2021 (11.20 AM)

Carpeting work along Budang malbasey soreng road is in progress.

 

Date: 09-March-2021 (07.41 PM)

Carpeting works under progress along Polok Hot Spring road km 1st under Rabong Sub Division.

 

Date: 03-March-2021 (07.52 PM)

Phongla Bermiok road and Nizrameen road carpeting in progress.

 

Date: 02-March-2021 (04.12 PM)

Carpeting work under progress along Kamrang Fatak towards Kamrang College road.

 

Date: 27-February-2021 (10.55 AM)

Work started at Ramam bridge

Work under progress along Wok Sikkip road below Kamrang fatak.

 

 

Date: 23-February-2021 (02.53 PM)

Site visit of Secretary  R&B, CE's  NH, SE NH, DE 's NH,  AE 's NH, JE NH along with contractor along Naya Bazaar Legship Road.

 

Date: 22-February-2021 (03.24 PM)

Protective work under progress at km 2nd along Magitar to Compound road carpeting work .

 

Date: 19-February-2021 (06.33 PM)

FWR from Khop to Dong recommenced and is under progress.

 

Date: 18-February-2021 (11.12 AM)

Laying of BC commenced along Singithang road at Namchi.

 

Date: 17-February-2021 (05.18 PM)

Work commenced for road surfacing along Kamrang Fatak to 1st turning.

 

Date: 16-February-2021 (01.58 PM)

Chalamthang to Rekep km 2nd in under progress.

 

Date: 14-February-2021 (07.20 PM)

Kholaghari to Jaubari road km 5th under progress.

Surface restoration works by laying cement concrete along various stretches of ringhim Gumpa road being executed on HMs direction.

 

Date: 13-February-2021 (05.30 PM)

Inspection of ongoing works along Namchi,Phongla,Mamring.

 

Date: 12-February-2021 (07.19 PM)

Inspection of Bojeck diversion work by Central team.

 

Date: 11-February-2021 (09.43 AM)

Site inspection is going on by the Director, MDoNER and his team for the road SKO2.

 

Date: 08-February-2021 (10.41 AM)

Drainage work under progress along Suntaley road in South Sikkim.

 

Work commenced along kholaghari Jaubari road.. km 4th to 8th

 

Date: 07-February-2021 (06.12 PM)

Minor Repair and rehabilitation works completed at JALIPOOL bridge.

 

Repairing works along Ringhim Gumpa road.

 

Welding and repair works continues at kali khola bridge with timely opening of traffic along Ranka Sichey road.

 

 

Date: 02-February-2021 (08.23 PM)

Work resumed at Namchi Rong Sumbuk road at ghatey khola.

 

 

Date: 01-February-2021 (05.54 PM)

Melli Kherabari carpeting work under progress.

 

 

Date: 30-January-2021 (08.58 PM)

Visit to Chewabhanzang with Chief Engineer S/W and Additional Chief Engineer S/W along DE Gayzing, AE Kaluk, Junior Engineers and Contractors.

 

Date: 30-January-2021 (11.49 AM)

5th lift Concreting in m35 mix design of Pier n mix filling towards approach  at Abutment (A1) at Khechedumra steel bridge in South Sikkim.

 
   

Date: 29-January-2021 (10.18 AM)

Magitar to Compound road  upgradation  work in South Sikkim  has been  started from today .

 

Date: 28-January-2021 (06.26 PM)

Hon'ble Minister for Roads and Bridges Department- Shri Samdup Lepcha, paid a site visit for the ongoing work for Double Lane at Adampool-Ranka Sichey road in East Sikkim. He was accompanied by PCE, Chief Engineer (N/E), ACE (N/E), SE (N/E), DE (E-I), AE ( Sub Div-IV), JE Incharge (Roads and Bridges) and concern contractor.

 

Date: 27-January-2021 (09.47 AM)

Departmental labours engaged along JALIPOOL bridge to Saramsa Garden for clearance of debris and drains.

 

Date: 25-January-2021 (11.33 AM)

Carpeting work along irrigation office to Lower Singling in progress.

 

Date: 24-January-2021 (12.53 PM)

Concreting in m35 of pier upto 3rd lift on progress at Khechedumra steel bridge in South Sikkim.

Retaining wall at Som slide completed. Now trafficable for all kind of traffic.

 

 

Date: 14-January-2021 (04.25 PM)

Current progress of 55m span steel bridge over Kali khola in South Sikkim.

 

Date: 11-January-2021 (02.45 PM)

Today Concreting in m35 at Raft of Pier is under progress of 117m span Khechedumra steel bridge in South West Sikkim.

 

Date: 08-January-2021 (04.27 PM)

Site visit by Assistant Engineer Jorethang sub division along with Melli station JE for inspection of ongoing work along Melli Kerabari Turuk Sadam Bhangyang road.

Hill cutting and site levelling work under progress at Kali khola bridge along Melli Passi Katyang road in South Sikkim.

Work under progress along Phongla Mamring road.

Restoration of road surface and clearance of slips under taken aling work Sikkip road.

 

Date: 07-January-2021 (07.48 AM)

Work under progress "Strengthening,Carpeting and drainage works along Melli Kherabari Turuk Sadam in South Sikkim " at km 3rd from Melli.

 

Date: 07-January-2021 (07.48 AM)

Site visit for various works in Dzongu North Sikkim by Secretary, PCE, CE, ACE, SE, DE along with field engineers and contractors.

           

 

Date: 06-January-2021 (09.10 PM)

Site visited by DE sir (Rabong  Division) along with AE sir for inspection of reinforcement work for abutment for the work Link road from Lower Payong to Middle Lingee via Lower Lingee under Yangang Sub Division.

 

 

Date: 04-January-2021 (04.51 PM)

New look of Sikkip suspension bridge.

 

Date: 02-January-2021 (03.18 PM)

Bailey bridge for two cut off GPUs inaugurated by Honble Minister in presence of other dignitaries and district officials and public.

 

Date: 23-December-2020 (11.22 AM)

2nd phase work-fitting fixing of suspender n f/f of 50mm wide Patti beat over cheaker plate under progress at Sikkip suspension bridge in South Sikkim.

 

 

Date: 21-December-2020 (02.29 PM)

Replacement and Fitting fixing of suspender is under progress at Sikkip bridge in South Sikkim .

 

Date: 10-December-2020 (11.40 AM)

Drone survey being carried out for a proposed road at fala gaon ,6th mile tadong under Tadong Constituency.

   

Maintenance  work carried out along Yangang Makha road. (Manzing Slide)(06.06 PM)

Inspection of ongoing restoration works along Phongla Mamring road along with JE and site supervisors.(08.16 PM)

 

Date: 04-December-2020 (08.47 AM)

Maintenance work under progress at Gufa Dara along Ralong Phamtam road under Rabong Sub Division.

 

Date: 01-December-2020 (05.05 PM)

Joint inspection was carried out at Sim khola bailey bridge along Ranka sichey road and Two lane adampool Highway by Principal chief Engineer Sir , Chief Engineer (N/E) , Additional chief engineer (N/E) , Superintendening Engineer (N/E) , Divisional engineer (East 1) accompanied by the concerned junior engineer and the contractors.

 

Date: 29-November-2020 (12.41 PM)

Labour and machine has been engaged at Dojok slide for maintenance work along Rabong Yangang Road.

Date: 29-November-2020 (06.30 PM)

Erection of crate wall nearing completion at sim khola bridge along Ranka sichey road.

 

Date: 26-November-2020 (11.04 AM)

The Sim Khola along Ranka Sichey road site was inspected by S.E (N/E) , concerned JE's of the department and the engineers of the contractor , and has directed to provide crate wall below the pedestal to strengthen the pedestal and prevent further occurrence of slip. Similarly ,thr contractor has been directed to provide the materials by evening so as to resume the progress at site on war footing  and to normalise the  traffic movement along Ranka sichey road by Monday.

Permanent restoration work under progress at 82m span  suspension  bridge over River Rangit at Sikkip in South Sikkim.

 

 

Date: 25-November-2020 (05.24 PM)

Construction of plum wall for the protection of R.C.C pedestal below the Bailey bridge over sim khola along Ranka Sichey road being done on war footing manner.

Restoration work along Phongla Mamring road has commenced today.

 

Date: 21-November-2020 (01.48 PM)

Cavity formed due to soil erosion below the R.C.C pedestal of Bailey bridge over sim khola along ranka sichey road , to avoid any casualties at site safety ribbon has been tied across the bridge and the traffic police have been informed.

 

 

Date: 21-November-2020 (05.23 PM)

Permanent restoration work under progress at Sikkip suspension bridge in South Sikkim.

 

 

Date: 20-November-2020 (06.21 PM)

The current progress of work of steel bridge over Dong khola between Harrabotey and Dong village in South Sikkim

 

Date: 18-November-2020 (12.05 PM)

Jorethang sub division getting  ready for permanent restoration work to  82m span suspension Bridge at sikkip over River Rangit in South Sikkim.

 

Date: 12-November-2020 (01.05 PM)

Casting of 25 MTR span RCC STEEL BRIDGE along GRS road ongoing

 

Date: 11-November-2020 (01.14 PM)

Earth work started from today dated 11.11.2020 at Dong khola for proposed  steel bridge .

 

Date: 10-November-2020 (07.58 AM)

Road sitrep- 10/11/2020

Roads under ADB

1.Jorethang to manpur road open sk01.

2.Jorethang to namchi road block at 10km to 18km road has diverted from CCCT chisopani fatak via Assangthang sk02.

SK-01: Open for Light and heavy vehicles.

SK-02: Open for Light and heavy vehicles upto Km10th and only for Light vehicles upto Km 15th.

Today Puja has been done before commencent of work at Dong Khola steel bridge site.

 

Date: 09-November-2020 (03.50 PM)

RCC Raft casting started in m35 (1:0.5:1) mix design .The detail reininforcement has been tested by Divisional Engineer on 3.11.2020 . The Two number of TM machine is using for concrete mixing . Each machine mixing 3m3 n 3.5m3 at a time at Khechedumra steel bridge .

 

Date: 06-November-2020 (08.25 AM)

Road sitrep- 06/11/2020

Gangtok Sub-Division

1.All roads under Gangtok sub division IV is trafficable.

Singtam Sub-division

1.Radang kimchithang road closed

2.Sawany Ralang pathang road-closed

3.Rest all roads are open under Singtam sub division.

Roads under ADB

1.Jorethang to Manpur road open sk01.

2.Jorethang to Namchi road block at 10km to 18km road has diverted from CCCT chisopani fatak via Assangthang sk02.

 

Date: 05-November-2020 (08.28 AM)

Road sitrep- 05/11/2020

Gangtok Sub-Division

1.All roads under Gangtok sub division IV is trafficable.

Singtam Sub-division

1.Radang kimchithang road closed

2.Sawany Ralang pathang road-closed

3.Rest all roads are open under Singtam sub division.

 Jorethang Sub-division

1. All road under Jorethang SD remain open except FWR

Namchi sub division

1.All major roads under Namchi sub division is open for traffic except few of the left out FWR to be cleared of slips that occured during this monsoon.

Roads under ADB

1.Jorethang to Manpur road open sk01.

2.Jorethang to Namchi road block at 10km to 18km road has diverted from CCCT chisopani fatak via Assangthang sk02.

Yangyang Sub-division

1.All roads are trafficable except some of the FWR.

2.Maintenance work carried out along Pabong Simchthang Yangyang road.

Today SE South and DE Namchi visited Khechedumra Bridge site .

Today SE South and DE Namchi visited Sikkip suspension bridge over River Rangit.

 

 

Date: 04-November-2020 (08.25 AM)

Road sitrep- 04/11/2020

Gangtok Sub-Division

1.All roads under Gangtok sub division IV is trafficable.

Singtam Sub-division

1.Radang kimchithang road closed

2.Sawany Ralang pathang road-closed

3.Rest all roads are open under Singtam sub division.

Roads under ADB

1.Jorethang to Manpur road open sk01.

2.Jorethang to Namchi road block at 10km to 18km road has diverted from CCCT chisopani fatak via Assangthang sk02.

Namchi sub division

1.All major roads under Namchi sub division is open for traffic except few of the left out FWR to be cleared of slips that occured during this monsoon.

Yangyang Sub-division

1.All roads are trafficable except some of the FWR.

Jorethang Sub-division

1. All road under Jorethang SD remain open except FWR

 

Date: 03-November-2020 (08.23 AM)

Road sitrep- 03/11/2020

 Singtam Sub-division

1.Radang kimchithang road closed

2.Sawany Ralang pathang road-closed

3.Rest all roads are open under singtam sub division.

 Gangtok Sub-Division

1.All roads under Gangtok sub division IV is trafficable.

Roads under ADB

1.Joerthang to Namchi road block at 10km to 18km road has diverted from CCCT chisopani fatak via Assangthang sk02.

2.Jorethang to Manpur road open sk01.

 

Site has been visited by SE Namchi along with DE Rabong, AE and concerned contractors at Dojok Diversion Road via Satam to Ravangla for work initiation under Yangang Sub-Division.

Road is clear at 10km Joerthang to Namchi road

 

 

 

Site visit was made to Science Center at Marchak by S.E(N/E) ,D.E (East 1)  in presence of the Junior Engineers and Supervisor at site for the ongoing  surface improvement works.

Date: 02-November-2020 (09.00 AM)

Road sitrep- 23/10/2020

 

Gangtok Sub-Division

1.All roads under Gangtok sub division IV is trafficable.

 

Jorethang Sub-DIvision

1. All road under Jorethang SD remain open except FWR.

 

Yangang Sub-Division

All roads are trafficable except some of the FWR.

 

Singtam Sub-Division 

1.Radang kimchithang road- closed

2.Sawany Ralang pathang road-closed

3.Rest all roads are open under singtam sub division.

 

 

 

 

Date: 23-October-2020 (09.00 AM)

Road sitrep- 23/10/2020

 

Gangtok Sub-Division

1.All roads under Gangtok sub division IV is trafficable.

 

Singtam Sub-division

1.Radang kimchithang road. closed.

2.Sawany Ralang pathang road-closed.

3.Rest all roads are open under singtam sub division.

 

Yangang sub-division

1.All roads are trafficable except some of the FWR.

 

Kaluk Sub Division 

1. Bermiok Legship road blocked at KM8 Ghungringay and KM18 Feng Khola

2. Reshi Rinchenpong road trafficable for light vehicles only

3.Rest of the roads are open.

 

Rabong Sub Division

1. Road blocked at Ch 11- Ch 14 along Legship to Tashiding Bridge, Vehicles may be diverted via the upper NHPC diversion.

2. Road blocked at km 4 along 10th Mile turning to tingmoo village road. Rest of the roads under Rabong Sub Division are open.

Jorethang Sub Division 

1. All road under Jorethang SD remain open except FWR.

 

At Km 4th ch 28 with concrete grade of M25 at reshithang (crematorium point) below Ranka sichey road

Men and machineries has been engaged for the surface improvement works at SCIENCE CENTER ,Marchak.

 

 

 

Date: 22-October-2020 (08.22 AM)

Road sitrep- 22/10/2020

 

Gangtok Sub-Division

1.All roads under Gangtok sub division IV is trafficable.

 

Roads under ADB

1. Jorethang to Manpur road open sk01.

2. Joerthang to Namchi road block at 10km to 18km road has diverted from CCCT chisopani fatak via Assangthang sk02.

 

Singtam Sub-division

1.Radang kimchithang road. closed.

2.Sawany Ralang pathang road-closed.

3.Rest all roads are open under singtam sub division.

Yangang sub-division

1.All roads are trafficable except some of the FWR.

Kaluk Sub Division 

1. Bermiok Legship road blocked at KM8 Ghungringay and KM18 Feng Khola

2. Reshi Rinchenpong road trafficable for light vehicles only

3.Rest of the roads are open.

Jorethang Sub Division 
1. All road under Jorethang SD remain open except FWR.

 

 

 

 

Date: 21-October-2020 (08.22 AM)

Road sitrep- 21/10/2020

 

Gangtok Sub-Division.

All roads under Gangtok sub division IV is trafficable.

Jorethang Sub-Division. 

1. All road under Jorethang SD remain open except FWR.

Roads under ADB.

1. Joerthang to manpur road open sk01.

2. Joerthang to namchi road block at 10km to 18km road has diverted from CCCT chisopani fatak via Assangthang sk02.

 

 

Date: 20-October-2020 (03.37 PM)

Khechedumra Bridge site ,placing of bar at west site Abutment  Raft and simultaneously foundation work under progress of pier in west side .

 

Date: 19-October-2020 (08.22 AM)

Road sitrep- 16/10/2020

 Namchi sub division

1. Namchi-Phongla-Mamring road .Open

2. Namchi-Wok -Sikkip .Open

3. Namchi- Rong -Sumbuk.Open

4. Phongla- Bermiok .Open

5. Chuba Perbing road .Open.

 

Rabong Sub-division

1. Road blocked at Ch 11- Ch 14 along Legship to Tashiding Bridge, Vehicles may be diverted via the upper NHPC diversion.

2. Road blocked at km 4 along 10th Mile turning to tingmoo village road.

3. Road trafficable for light vehicle only at Rabong Legship road (NH 510) under NHIDCL.

4. Most of the fair weather roads are blocked due to some major and minor slips. Rest of the roads under Rabong Sub Division are open.

Yangang sub-division

1.All roads are trafficable except some of the FWR. 

Singtam Sub-division

1.Radang kimchithang road. closed

2.Sawany Ralang pathang road-closed

3.Rest all roads are open under singtam sub division.

Gangtok Sub-Division

1.One way vehicular movement at Km 3 along GRS road ,rest all roads under Gangtok sub division IV is trafficable.

 

Kaluk Sub Division

1.Bermiok Legship road blocked at KM8 Ghungringay and KM18 Feng Khola.

2.Reshi Rinchenpong road trafficable for light vehicles only

3.Rest of the roads are open.

 

Jorethang Sub Division

1. All road under Jorethang SD remain open except FWR.

Roads under ABD.

1.Joerthang to manpur road open sk01.

2.Jorethang to namchi road block at 10km to 18km road has diverted from CCCT chisopani fatak via Assangthang sk02.

 

Maintenance work along Rabongla to Yangang is under progress at several stretches.

 

Date: 18-October-2020 (10.38 AM)

Laying of B.M at km 4th (2mile stretch ) along GRS road.

Maintenance work of sunkdown portion at Shalelay to improve the riding comfort under progress along Rabong Ralong.

 

Date: 16-October-2020 (08.00 AM)

Road sitrep- 16/10/2020

Namchi Sub division.

1. Namchi-Phongla-Mamring road .Open

2. Namchi-Wok -Sikkip .Open

3. Namchi- Rong -Sumbuk.Open

4. Phongla- Bermiok .Open

5. Chuba Perbing road .Open.

 

Rabong Sub-division:

1. Road blocked at Ch 11- Ch 14 along Legship to Tashiding Bridge, Vehicles may be diverted via the upper NHPC diversion.

2. Road blocked at km 4 along 10th Mile turning to tingmoo village road.

3. Road trafficable for light vehicle only at Rabong Legship road (NH 510) under NHIDCL.

4. Most of the fair weather roads are blocked due to some major and minor slips. Rest of the roads under Rabong Sub Division are open.

 

Daramdin Sub-Division.

1.All the road under Daramdin Sub Division are open as of now.

 

Singtam Sub-division:

1.Radang kimchithang road- closed

2.Sawany Ralang pathang road-closed

3.Rest all roads are open under singtam sub division.

 

Yangang Sub-division.

1. Most of the FWR are blocked due to major and minor slips.

2. Rest all of the roads are open as of now.

 

Kaluk Sub Division:

1.Bermiok Legship road blocked at KM8 Ghungringay and KM18 Feng Khola.

2.Reshi Rinchenpong road trafficable for light vehicles only.

3.Rest of the roads are open.

 

Gangtok Sub-division:

One way vehicular movement at Km 3 along GRS road ,rest all roads under Gangtok sub division IV is trafficable.

 

Temporary repair work under progress at 82mtr span suspension bridge over River Rangit at Sikkip.

 

 

Date: 15-October-2020 (08.30 AM)

Road sitrep- 15/10/2020

 Namchi Sub division.

1. Namchi-Phongla-Mamring road .Open

2. Namchi-Wok -Sikkip .Open

3. Namchi- Rong -Sumbuk.Open

4. Phongla- Bermiok .Open

5. Chuba Perbing road .Open

 

Yangang Sub-division.

1. Most of the FWR are blocked due to major and minor slips.

2. Rest all of the roads are open as of now.

 

Rabong Sub-division:

1. Road blocked at Ch 11- Ch 14 along Legship to Tashiding Bridge, Vehicles may be diverted via the upper NHPC diversion.

2. Road blocked at km 4 along 10th Mile turning to tingmoo village road.

3. Road trafficable for light vehicle only at Rabong Legship road (NH 510) under NHIDCL.

4. Most of the fair weather roads are blocked due to some major and minor slips. Rest of the roads under Rabong Sub Division are open.

 

Singtam Sub-division:

1.Radang kimchithang road- closed

2.Sawany Ralang pathang road-closed

3.Rest all roads are open under singtam sub division.

 

Gangtok Sub-division:

One way vehicular movement at Km 3 along GRS road ,rest all roads under Gangtok sub division IV is trafficable.

 

Kaluk Sub Division:

1.Bermiok Legship road blocked at KM8 Ghungringay and KM18 Feng Khola.

2.Reshi Rinchenpong road trafficable for light vehicles only.

3.Rest of the roads are open.

 

Jorethang Sub Division:

1. All road under Jorethang SD remain open except FWR .

2 All FWR blocked

 

Melli Kherabari road now trafficable for light vehicle after filling huge quantity of muck at 3rd km sunk down point which has been bought within 10km radius .

 

Excavation work for 25mtr span 70 R loading bridge over seti khola at km 3rd ch 15th along Ranka sichey road commences from today i.e 15/10/20.

 

 

 

 
 
 

 Road Network under Roads and Bridges Department